+27 18 771 5589

SHOTCRETE ENGINEERING OVERVIEW EFNARC-ALIGNED TECHNICAL SUMMARY

This page provides a practical engineering overview of sprayed concrete systems used in underground mining and civil construction. Each section links to detailed technical articles within the RSS Mining Engineering Resources library.

1. Shotcrete fundamentals

(Full Article – Shotcrete Fundamentals)

Shotcrete is concrete projected at high velocity and compacted by impact energy rather than vibration.

• Typical projection velocity exceeds 20 m/s
Practical example: reducing air volume lowers velocity and causes aggregate bounce rather than embedment.

• Early structural support is achieved rapidly
Practical example: with correct accelerator dosage, early strength of approximately 0.5 MPa can be reached within 1 to 2 hours.

• Shotcrete works as part of a support system
Practical example: 75 mm fibre reinforced shotcrete combined with 2.4 m rock bolts at 1.2 m spacing.


2. Wet shotcrete process and pumping system

(Full Article – Equipment Systems and Pumping Mechanics)

Wet shotcrete is mixed with water before pumping and transported hydraulically to the nozzle.

• Typical pump outputs range from 8 to 30 m³ per hour
Practical example: a piston pump delivering 20 m³ per hour requires stable rheology to avoid surging at the nozzle.

• Practical pumping distances range from 120 to 250 m
Practical example: at distances beyond 200 m, pressure increases and segregation risk becomes significant.

• Accelerator is introduced at the nozzle
Practical example: 400 kg cement per m³ requires approximately 16 to 32 kg accelerator at 4 to 8 percent dosage.


3. Shotcrete mix design and material behaviour

(Full Article – Mix Design and Material Interaction)

Shotcrete mixes must remain pumpable while adhering to vertical and overhead surfaces.

• Cement content typically 380 to 450 kg per m³
Practical example: 400 kg per m³ provides sufficient paste to embed fibres.

• Aggregate grading normally limited to 0 to 8 mm
Practical example: oversized aggregate increases rebound at the crown.

• Water cement ratio typically 0.40 to 0.45
Practical example: increasing to 0.55 may reduce 28-day strength by more than 20 percent.

• Silica fume typically 6 to 10 percent of cement
Practical example: 32 kg per m³ improves cohesion and reduces fibre rebound.


4. Substrate preparation and rock interaction

(Full Article – Substrate Preparation and Ground Conditions)

Shotcrete performance depends on bond to competent rock.

• Loose rock must be removed prior to spraying
Practical example: a 20 mm loose slab behind shotcrete can cause full lining delamination.

• Surfaces must be washed down before spraying
Practical example: drilling dust creates a slip plane between rock and lining.

• Rock surface must be damp, not dry or flowing
Practical example: dry rock absorbs water from the paste, weakening bond.


5. Application mechanics and nozzle technique

(Full Article – Application Mechanics and Nozzle Technique)

Application technique governs compaction and rebound.

• Nozzle angle should remain close to 90 degrees
Practical example: spraying at 70 degrees can increase rebound by over 30 percent.

• Stand-off distance typically 1.5 to 2.0 m
Practical example: spraying at 3.0 m reduces impact energy and causes sloughing.

• Spraying must begin at the bottom and work upward
Practical example: crown-first spraying leads to rebound contamination in lower layers.


6. Layer build-up and thickness control

(Full Articles – Quality Control Systems, Testing Methods, And Performance Verification)

Shotcrete thickness must be developed progressively.

• Typical layer thickness 40 to 60 mm
Practical example: attempting 120 mm in one pass causes sagging.

• Design thickness typically 50 to 150 mm
Practical example: 75 mm fibre shotcrete commonly used in development ends.

• Thickness verified by continuous probing
Practical example: probe every 1 to 2 m during spraying.


7. Rebound behaviour and performance indicators

(Full Article – Rebound Engineering, Measurement Methods, And EFNARC Monitoring Requirements)

Rebound is a key indicator of application efficiency.

• Typical rebound values
Sidewalls 5 to 10 percent
Overhead areas 10 to 20 percent

• Increasing rebound indicates loss of control
Practical example: increase from 10 to 18 percent suggests nozzle angle deviation.

• Visual estimation is unreliable
Practical example: measured rebound often differs by more than 8 percent from visual judgement.


8. EFNARC rebound measurement methodology

(Full Article – Rebound Engineering, Measurement Methods, And EFNARC Monitoring Requirements)

EFNARC requires rebound to be measured using the weighing method.

• Plastic sheeting must extend 10 percent beyond test area
Practical example: 10 m² sprayed area requires at least 11 m² sheeting.

• Minimum sprayed thickness for testing is 50 mm
Practical example: thinner layers give inaccurate volume calculation.

• Rebound calculation example
Sprayed volume 1.5 m³
Wet density 2300 kg per m³
Total sprayed mass 3450 kg
Rebound collected 500 kg
Rebound result 14.5 percent.


9. Quality control testing and verification

(Full Article 7 – Quality Control Systems)

Testing verifies structural performance.

• Flow test target typically 500 to 600 mm
Practical example: flow below 450 mm increases blockage risk.

• Compressive strength typically 40 MPa at 28 days
Practical example: lower results indicate excess water or poor curing.

• Energy absorption commonly ≥ 700 joules
Practical example: achieved using 40 kg per m³ steel fibres.

• Thickness verification during spraying
Practical example: real-time probing prevents under-application.


10. Equipment inspection and reliability

(Full Article 8 – Equipment Inspection and Maintenance)

Equipment stability directly affects lining quality.

• Delivery hoses typically limited to 10 m lengths
Practical example: long hoses increase pressure fluctuation.

• Clamp safety pins mandatory at every joint
Practical example: missing pins allow clamp opening under pressure.

• Greasing required at start of each shift
Practical example: two grease strokes per nipple prevents hinge seizure.


11. Blockage control and pressure safety

(Full Article – Shotcrete Safety Systems, Risk Control, and Underground Work Practices)

Blockages represent high stored energy risk.

• Pump pressure commonly 60 to 75 bar
Practical example: uncontrolled hose rupture can cause fatal injury.

• Blockages must never be pushed forward
Practical example: pump reversal releases pressure safely.

• Air must be isolated before intervention
Practical example: residual air can eject concrete violently.


12. Shotcrete safety systems

(Full Article – Shotcrete Safety Systems, Risk Control, and Underground Work Practices)

Shotcrete requires strict safety controls.

• Exclusion zones during spraying mandatory
Practical example: no personnel beneath fresh shotcrete for minimum 2 hours.

• PPE required at all times
Practical example: goggles prevent accelerator splash injuries.

• Ventilation required
Practical example: poor airflow increases chemical exposure risk.


13. Training, competence, and performance control

(Full Article 10 – Training and Competence)

Shotcrete performance depends on people.

• Operator skill can change rebound by more than 10 percent
Practical example: trained operator achieves 8 percent, untrained 18 percent.

• Training improves productivity
Practical example: output increases from 12 to 20 m³ per hour.

• Certified operators improve consistency
Practical example: fibre dosage remains within design tolerance.


14. Engineering outcome when EFNARC principles are applied

When shotcrete is executed according to EFNARC guidance:

• Rebound typically reduces by 30 to 50 percent
• Thickness compliance improves
• Material waste decreases
• Safety incidents reduce
• Structural reliability increases

This knowledge hub provides the technical foundation for consistent, safe, and durable sprayed concrete support systems.